Home / News / How to check the installation dimensions of the reducer: shaft extension, keyway, anchor hole and drawing confirmation list - Hangzhou Weigao Transmission

How to check the installation dimensions of the reducer: shaft extension, keyway, anchor hole and drawing confirmation list - Hangzhou Weigao Transmission

Author: Site Editor     Publish Time: 26-10-2026      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
sharethis sharing button

The installation size of the reducer is incorrect, and it cannot be installed no matter how accurate the model is.

SelectionAfter calculating the torque, speed ratio and thermal power, we only determined 'which gear to use'. Whether it can land on the ground depends on the installation size of the reducer . Failures in on-site installation are usually divided into three categories: the geometric interface is misaligned, the distance between the foot holes, the center height, and the shaft extension do not match the original equipment; the tolerance fit is not read thoroughly, the shaft extension mark k6 is processed according to h6, and the coupling H7 hole is loose when installed; there is not enough space left, the oil drain plug is attached to the foundation, and the vent cap top shield is attached. The first two types can be stopped with a drawing and a caliper before ordering. When they arrive at the site, they find that they can only expand the hole, add a backing plate or even change the model.

Six interface parts that must be checked one by one

Interface part

drawing elements

Frequently Asked Questions

as a result of

Footing hole spacing and hole diameter

A1×B1, n-φd

Hole distance deviation ≤±0.5 mm, bolt verticality ≤0.5°

The holes don"t match up, so we can only expand the holes.

Center high

h

Mark the value according to the GA diagram and check the diagonal by actual measurement.

The pad iron is hard to form a soft foot , and the bearing is eccentrically loaded.

Output shaft extension

d×l, key b×h

For d≤50 mm, take k6, for d>50 mm, take m6, and the key width is h8.

Failed to install or crashes after running

input flange

Stop, screw hole PCD

Stop b1≤230 mm uses j6, >230 mm use h6

The motor is installed incorrectly and the vibration exceeds the standard.

Hollow shaft hole

d. Keyway width

Bore diameter H7, groove width shaft N9, hub JS9

The shaft sleeve does not advance or slips

Attachment orientation

Oil plug, oil mark, breather cap

Changes with installation orientation M1~M6

Oil change requires lifting equipment

How to read tolerance: k6, m6, H7 and keyway width

What is easy to overlook in dimensioning is the 'tolerance zone is bound to the diameter': both are k6, the 45 mm axis is +0.018/+0.002 mm, and the 70 mm axis is +0.030/+0.011 mm according to m6. If you copy the markings, you will make out-of-tolerance parts. The general method is to use k6 for solid shaft ≤50 mm, m6 for >50 mm, and the hollow shaft hole H7 to match the customer shaft h6. Taking 60 mm as an example, the gap falls between 0.019~0.049 mm, which can be pushed forward without shaking. The keyway is taken according to GB/T 1096: a 70 mm shaft is equipped with a 20×12 flat key, the groove depth is 7.5 mm, the key width is h8, the shaft groove width is N9 (0~-0.052 mm), the hub groove width is JS9 (±0.026 mm), and the symmetry is controlled within 0.03 mm. Otherwise, the key will be deflected in the groove and the torque will only be borne by one edge.

The flange seam determines the coaxiality of the motor and the reducer. If the seam or PCD is out of tolerance, it will look good when installed. The measured runout is above 0.1 mm, and the bearings and oil seals will fail prematurely. The hole diameter, keyway and locking method of the hollow shaft must be checked at the same time, and axial space must be reserved for the disassembly and assembly of the shrink disk structure.

Seven items to check for a GA chart

Check items

What to look for on the drawing

Judgment points

Installation orientation

M1~M6 code and oil level line

Consistent with the on-site attitude, the oil level can be observed

footing

A1×B1, hole diameter, bolt specifications

Correspond to the reserved holes in the foundation, leaving 2~3 mm

Center high

h and shaft extension centerline

Consistent with the original equipment elevation

Shaft extension

d×l, key b×h, center hole

Center hole GB/T 145 C type, key length covers the hub

flange

Stop, PCD, screw hole depth

Comparison with actual measurement of motor flange

appendix

Oil plug, oil mark, breather cap, lifting lugs

Leave operating space around

Weight and center of gravity

Net weight, center of gravity elevation

The basic load capacity is not less than 3 times the weight of the entire machine

Five steps for on-site retesting

After the drawings have been verified, they must be remeasured on site. First, clean the base surface to remove burrs and oil stains, use a knife-edge ruler and a feeler ruler to check the flatness , control it within 0.1 mm/m, and the bonding area should not be less than 75%. Second, measure the hole spacing twice along the diagonal and take the average, and the deviation is controlled within ±0.5 mm. Third, measure the center height of the height ruler and benchmark it with the original equipment. If the difference is more than 3 mm, do not rely on the pad iron to align it. Instead, add equal thickness pads to the entire surface. Fourth, use a micrometer to measure the shaft extension size and roundness, and a caliper to measure the key width and groove width. Fifth, manually turn the car for one or two turns to confirm that there is no jamming, and then check whether the oil plug and oil mark are within reach.

Four common pitfalls and costs

The center height difference is 3 mm, and the inclined pad iron is used as a hard pad. When the anchor bolts are tightened, the box will be stretched and deformed by 0.1~0.2 mm. The raceway will be eccentrically loaded and the oil seal will be eccentrically worn. The key length is 10 mm shorter than the effective length of the hub, and the pressure is insufficient. The key is sheared and the shaft extension is sprained under impact conditions. The oil drain plug faces the foundation, and the equipment must be lifted every time the oil is changed. The gap between the motor flange and the gap is 2 mm, which needs to be flattened by bolts, and the coaxiality is damaged. Tighten according to the 8.8 grade bolt torque: 45~55 N·m for M12 and 120~140 N·m for M16. Tighten diagonally to the rated value in two or three times, and retighten once every 24 hours.

Only when the contract and drawings are written down can it be considered successful.

Sign and confirm the GA drawing as an attachment to the contract. The model, speed ratio, installation orientation, shaft extension and key, flange stopper, oil plug orientation and weight are indicated on the drawing. Changes must be confirmed in writing. Before shipment, review the drawing according to the drawing and keep records. Upon arrival, unpack and randomly inspect the shaft extension diameter, key width and anchor hole spacing. Any deviations shall be reported during the acceptance period.

The order is worth remembering: first check the footing and center height , then check the shaft extension and keyway , and finally check the accessories and maintenance space - the first two determine whether it can be installed, and the latter determines whether it can be maintained in the future. Hangzhou Weigao Transmission can provide GA drawings and dimensional tables of hard-toothed surface reducers , 、cycloidal pinwheel reducers , worm gears and gear reduction motors, etc., and supports customizing shaft extensions, flanges and foot arrangements according to customer interfaces. When replacing an in-service model, send the original machine nameplate and actual measured dimensions, and the reducer manufacturer can provide Selection and size verification services free of charge.

Latest News

WeiGao Transmission

Weigao Gear Reducer is an alliance group company that integrates research and development, production, sales, and service

+86 400 801 9158

Email: sales@wgt.net.cn;wgt.net.cn@gmail.com
Tel:+86571 85023000

WEIGAO REDUCER

FEEDBACK