Home / News / How to carry out dynamic inspection after FAF98-4KW-140-M4 gear reducer is installed

How to carry out dynamic inspection after FAF98-4KW-140-M4 gear reducer is installed

Author: Site Editor     Publish Time: 02-11-2026      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
sharethis sharing button
How to carry out dynamic inspection after FAF98-4KW-140-M4 gear reducer is installed

1. No-load dynamic inspection

During the no-load phase, it is necessary to disconnect the output terminal from the load and run continuously for 10 to 30 minutes, focusing on monitoring 4 indicators:

1. Noise detection‌: Measure with a sound level meter 1 meter away from the equipment. The normal sound should be uniform gear meshing, without sharp whistling, impact or periodic noise, and the noise value is ≤85dB‌.

‌2. Vibration detection‌: Use a vibration meter to detect the effective value of the vibration speed of the housing bearing position. It must be ≤‌2.8mm/s‌ and there should be no obvious resonance or local abnormal vibration.

‌3. Temperature monitoring‌: Use an infrared thermometer to track the temperature of the box and bearing seat. The maximum temperature during no-load operation does not exceed ‌80℃‌, and the temperature difference with the ambient temperature is ≤40℃, and there is no local sudden temperature rise.

‌4. Seal status inspection‌: Observe the shaft end oil seal, box joint surface, and oil level gauge position throughout the entire process. There is no new oil leakage or trace of oil leakage, and the breather cap is not blocked.

2. Dynamic inspection of graded loads

After passing the no-load condition, it will be gradually loaded to the rated load in 2 to 3 levels. Each level will run stably for 30 minutes. Three core verification items:

1. Vibration and temperature rise monitoring: The effective value of vibration speed under rated load still needs to be ≤2.8mm/s. The lubricating oil temperature is stable at 60~80℃. If it exceeds 90℃, the machine must be stopped immediately for investigation.

‌2. Transmission performance verification‌: Confirm that the transmission at the output end is stable, without loss of rotation or jamming, and the supporting motor current is stable within the rated range without significant fluctuations.

‌3. Abnormal status check‌: There is no carbonization of lubricating oil, burnt smell of overheated bearings, loose bolts, shell deformation and other abnormal conditions throughout the process.

3. Shutdown and re-inspection after dynamic inspection

After a total of 2 to 4 hours of load test operation, stop the machine and cool it to room temperature to complete the final verification:

1. Use a torque wrench to recheck all anchor bolts and coupling bolts to confirm that they are not loose and that the torque value complies with the instructions.

2. Extract a small amount of oil to check whether there are any metal chips or lumpy impurities. If metal particles are found, the machine needs to be disassembled to check the wear of gears and bearings.

3. Retest the coaxiality of the input and output shafts to confirm that the installation datum has not shifted and the shaft alignment accuracy still meets the requirements.

Latest News

WeiGao Transmission

Weigao Gear Reducer is an alliance group company that integrates research and development, production, sales, and service