Gearbox Housing Casting Lead Time: Pour Weight, Pattern Slots, 2027 Windows

Author: Site Editor     Publish Time: 06-11-2026      Origin: Site

Inquire

facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
sharethis sharing button

Most buyers assume a gearbox lead time is set by gear cutting or by bearings. The date is set by a moulding flask: the gearbox housing casting must wait for a pour, a shakeout and a stress relief cycle before any metal is cut. Gears can be scheduled around a weekend; a 950 kg housing cannot. Here is how the 20–40 week window builds.

Why the Housing Outruns the Gears

Three properties make the housing the critical path. It is single-sourced per pattern, so a new centre distance means new tooling. Its walls are thick, so the metal stays in the mould for a day. And it is front-loaded: nothing downstream — boring, gear cutting, the test to ISO 20816-9 vibration limits — starts until the casting is fettled and stress-relieved.

A second-order effect is rarely priced in: raising duty class — service factor gearbox selection from 1.5 to 1.75 under AGMA 6013 practice — steps up one frame size, which usually crosses a pour weight boundary and adds four to eight weeks.

Chvorinov's Rule Sets the Flask Time

Chvorinov's rule gives solidification time directly: t = B × (V / A)², with V/A the casting modulus and B the mould constant — about 0.9 min/mm² for grey iron in green sand. For a plate of thickness s the modulus is s/2, so double the wall and you quadruple flask time.

A 45 mm bearing wall has a modulus of 22.5 mm: 0.9 × 22.5² = 456 min, or 7.6 hours. A 70 mm mounting flange: 0.9 × 35² = 1,103 min, or 18.4 hours. The flange governs, so that pattern holds a flask for more than 18 hours — one moulding day. Wall thickness, not tonnage, is what the foundry sells.

Pour Weight Classes and Their Queue Behaviour

Gearbox foundry capacity is really a question about which line your housing lands on, because each class runs on different equipment.

Pour weight

Moulding route

Changeover

Typical batch

Slot response

≤ 50 kg

Flaskless automatic line

20–40 min

500–2,000 pcs

2–4 weeks

50–300 kg

Automatic line, 800 mm flask

1–2 h

200–600 pcs

3–6 weeks

300–1,000 kg

Floor moulding, 1,600 mm flask

4–8 h

50–150 pcs

8–16 weeks

1,000–3,000 kg

Two-box floor pour

1–2 days

20–60 pcs

12–20 weeks

> 3,000 kg

Pit moulding, mould drying

3–5 days

5–20 pcs

16–26 weeks

The jump between the second and third row catches projects: below 300 kg patterns change twice a day; above it you need a flask, a crane and a moulder.

Decomposing a 20–40 Week Window

These are booking windows our order desk quotes for Q4 2026 enquiries — foundry and machine-shop slots, excluding freight and customs.

Stage

Weeks

What drives it

Pattern, core boxes, first article

4–7

New foot pattern, riser layout, NDT report

Foundry slot wait

6–16

Position in the pattern campaign, not tonnage

Pour, shakeout, fettling

0.5–1

18 h in mould, gating removal, grinding

Stress relief and NDT

1–2

26 h cycle plus shared-furnace queue

Machining

3–4

Boring mill queue, two setups

Gear cutting, carburising, grinding

3–5

Case depth 1.6–2.0 mm, 24–36 h per load

Assembly, FAT, paint

1–2

Loaded run, vibration records

Total

19–37

Reuse an existing pattern and it drops by 4–7

Worked Example: A 620 kg Housing That Pours 912 kg

Take a three-stage helical unit, 250 kW at 1,500 rpm input, 42 rpm output, housing 620 kg in HT250 to GB/T 9439.

1. Pour weight. With gating, risers and feeders the pouring yield is about 68%: 620 / 0.68 = 912 kg. Add 4% foundry rejection and the foundry melts 912 / 0.96 = 950 kg per good casting.

2. Class. 912 kg lands in the 300–1,000 kg band: floor moulding, 1,600 × 1,250 flask.

3. Flask occupancy. With the flange at 18.4 h and six flasks on the bay, it yields six housings per moulding day, about 30 a week; a 30-unit order takes 7.5 flask-days.

4. The surprise. 30 × 950 kg = 28.5 t, or 0.24% of a 12,000 t/year foundry's output. You queue on changeover, not capacity: the order waits until another 120 housings of that pattern accumulate — that is where the 8–16 weeks go.

You Wait on Changeover, Not Capacity

That is the key sentence in any gear reducer delivery window negotiation: tonnage never constrains an order this size, so "the foundry is full" usually means "your pattern is not scheduled".

Ask for the campaign date, not the capacity number. A foundry running your pattern in week 6 and again in week 26 has told you your real window; one quoting "8 weeks" without a date quotes an average. A dedicated run at a 150-piece minimum buys 6–10 weeks for the cost of storing 120 housings — the logic behind critical spare holding across an industrial gearbox fleet.

Stress Relief and Machining: The Silent Weeks

Stress relief runs at 550–600 °C, holds about one hour per 25 mm of section — three hours for a 70 mm flange — then cools at no more than 30 °C/h to 200 °C: 11 h heating + 3 h hold + 11.7 h cooling ≈ 26 hours. Furnaces are shared across the order book, so a two-day cycle becomes a two-week wait.

Machining follows the largest bore, because that sets the machine. A Ø320 mm bore with 6 mm allowance needs two setups on a horizontal boring mill, 6–8 hours of cut and a queue three weeks deep. Casting distortion surfaces here too — a housing that moved 1.5 mm is re-clamped and re-indicated, which is why the first-article report belongs before machining, not with the shipment.

What to Lock Before You Sign

Lever

Weeks saved

Trade-off

Reuse an existing pattern and foot layout

4–7

Centre distance and shaft heights fixed by the old design

Pay for a dedicated pattern campaign

6–10

150-piece minimum, ~120 housings in stock

Split the order 40 / 60

4 on first units

Two acceptance tests, two shipments

Step down one catalogue frame size

6–9

Service factor drops from 1.75 to about 1.6

Fabricated steel housing

8–12

15–25% higher cost, weld fatigue at the torque bracket

Three clauses beat any expediting call: a campaign date with a penalty, a pattern ownership clause so tooling can move to a second foundry, and a first-article report released before machining. Together they turn a range into a date.

Order Windows, Not Tonnes

The 20–40 week band is tooling, a campaign slot, a 26-hour furnace cycle and three machine queues added up. Buyers who know gearbox housing casting is scheduled by pattern, not tonnage, ask for campaign dates, accept a standard frame size to keep a running pattern, and buy gear reducer maintenance spares while the pattern is hot.

For drives where the window matters — retrofits, replacement units, rollouts — WGT (Hangzhou Weigao Transmission) quotes housing pour weight, pattern status and campaign date with the technical offer, on helical, bevel-helical, planetary and cycloidal reducers, including drop-in SEW / NORD / Flender compatible replacement units. Run the duty through the online gearbox selection system, then send the frame size for its pour class.

Latest News

WeiGao Transmission

Weigao Gear Reducer is an alliance group company that integrates research and development, production, sales, and service

+86 400 801 9158

Email: sales@wgt.net.cn;wgt.net.cn@gmail.com
Tel:+86571 85023000

WEIGAO REDUCER

FEEDBACK