How to write a reducer procurement technical agreement: parameter list, acceptance terms and scope of supply - Hangzhou Weigao Transmission

Publish Time: 2026-10-24     Origin: Site

The most common problem The model number was written correctly, the price was negotiated, and the goods arrived. Three months after installation, it was found that the oil temperature was high, the noise exceeded the standard, and the coupling was not supplied. When I looked back at the agreement, there was only one sentence 'in line with national standards' written in it. What these types of disputes have in common is that there is no judgment value in the agreement that can be measured with an instrument.when buying a reducer is often not the price comparison, but the few pages of the technical agreement.

The essence of a technical agreement is to turn 'I thought' into 'a number signed and confirmed by both parties'. It does not need to be written as a long paper, but six types of information about the reducer must be put on paper: scope of supply, working condition parameters, reference standards and judgment values, test and witness methods, packaging and transportation, warranty and breach of contract liability. The following is an item-by-item breakdown of these six chapters, with three tables that can be directly applied.

1. Structure of six chapters: draw boundaries first, then talk about indicators

It is recommended that the order of chapters of the agreement be fixed, and be reviewed chapter by chapter to avoid omissions. The scope of supply solves "who supplies what"; working conditions and parameters solve "what to choose"; standards and acceptance solves "how to judge qualified"; testing and witness solves "who will test and when"; packaging and transportation solves "who is responsible if it breaks on the road"; warranty and penalties solves "what happens if something goes wrong".

Among the six chapters, the two chapters that are easily skipped are the scope of supply and test testimony. The former leads to the "missing backstop" debate, and the latter leads to the "you say it"s unqualified, I say it"s qualified" deadlock. The effort of two pieces of paper can save several months of coordination later.

2. Parameter table: write the working conditions into numbers that can be verified

The parameter table is not a sample copy, but a translation of the conditions at the usage site into Selection for input. By filling out one less item, the supplier will have more room for discretion. The following table shows the twelve common fields in the reducer Selection stage, and the consequences of missing them.

Field

Fill in requirements and examples

Consequences of missing information

Purpose and equipment

Such as "main drive of apron feeder", with a simplified diagram of working conditions attached

Select according to general working conditions, lifespan will be cut in half under impact conditions

Motor power/speed

P=30 kW, n₁=1470 r/min, including frequency conversion range

Unable to calculate thermal power, low speed section is prone to overheating

Output speed/speed ratio

n₂=32 r/min, i≈45.9, ±3% allowed

After the speed ratio is rounded up, the production capacity does not meet the standard.

Load properties

Constant torque/square torque/constant power, starting frequency

The service coefficient value is too small, and the tooth surface is pitted early.

Daily running time

24 hours continuous/8 hours single shift/intermittent

Thermal Balance Calibration Distortion

Service factor fs

Uniform 1.0~1.25, medium impact 1.4~1.6, heavy impact 1.75 or more

Rated torque is enough, peak torque is not enough

Installation method and location

M1~M6, horizontal/vertical, the oil level and breather cap direction change accordingly

The oil level mirror is in the wrong position and the actual oil level is insufficient.

Output shaft connection

Solid shaft flat key/hollow shaft expansion sleeve/spline/shrink disc

Interface does not match, on-site modification

Radial and axial loads

Cantilever force Fr, axial force Fa and action point distance

If the bearing is selected too small, it will fail early.

environmental conditions

Ambient temperature, altitude, dust, humidity, corrosion level

Insufficient insulation and heat dissipation margin

Protection and cooling

IP55, natural cooling/fan/oil cooling/water cooling

Forced to operate at reduced load during high temperature season

Lubricants and coatings

Mineral oil ISO VG220, dry film ≥100 μm

Mixed oil products, paint film and salt spray do not pass the test

In the torque column, be sure to indicate whether it is output torque or motor side torque. Calculated according to T₂=9550×P×i×η/n₁, when 30 kW, i=45.9, η=0.96, T₂≈8600 N·m; then multiplied by the service factor 1.5, the Selection torque should be calculated as 12 900 N·m for the machine base, not 8600 N·m. If this number is written incorrectly, the entire other terms of the agreement will be meaningless.

3. Standards and acceptance: write the standard number, write the grade, and write the judgment value

The sentence 'in line with national standards' is not enforceable at the acceptance site, because the same indicator in the national standard is often divided into multiple levels. The correct way to write it is in three stages: reference standard number + adoption level + judgment value. The commonly used acceptance indicators and corresponding calibers of reducers are shown in the table below.

Acceptance items

Reference standards

Recommended judgment value

Gear accuracy

GB/T 10095.1

Industrial general grade 8, precision transmission grade 6~7

contact spots

GB/Z 18620.4

Tooth height direction ≥70%, tooth length direction ≥90% (inspection under rated load)

no-load noise

GB/T 6404.1

1 m away from the center plane of the cabinet, A weighting ≤ 85 dB (A), small specifications are tightened step by step according to the sample

vibration

GB/T 6404.2

Not lower than grade C; the effective value of the speed at the bearing seat is ≤2.8 mm/s (ordinary accuracy)

No-load temperature rise

Product standards/agreement

Oil pool ≤ 35 K, bearing ≤ 40 K

Load temperature rise

Product standards/agreement

The upper limit of oil temperature is 65~80 ℃, and the upper limit of bearing is 85~90 ℃ (according to the model caliber)

Sealing

JB/T 7929

0.03 MPa, hold pressure for 20 s, pressure drop ≤5×10⁻⁵ MPa; no leakage on the joint surface

cleanliness

JB/T 7929

Class C (precision models can be upgraded to Class J)

Transmission efficiency

JB/T 5558

Each level of cylindrical gears is ≥98%; planetary level one is 98.5%, level two is 97%, and level three is 95.5%

Shaft extension radial circular runout

GB/T 1184

≤IT9, measured by dial indicator

coating

GB/T 9286

Total dry film thickness ≥100 μm, adhesion level 1

The judgment value must be followed by a measurement condition, otherwise it will still be an empty clause: the noise measuring point is 1 m away from the box, and the background noise is more than 10 dB(A) lower than the measured value; the temperature rise is based on thermal balance, and the temperature change of each measuring point within 30 minutes is considered stable if the temperature change of each measuring point is ≤1°C; the vibration measuring points are in three directions of the bearing seat. Without writing these conditions, the same machine can produce two sets of conclusions.

4. Testing and Witness: What is done at the factory and what is done on site

Each reducer should undergo a no-load test before leaving the factory: forward and reverse operation at rated speed for no less than 1 hour (some product standards require 2 hours). During this period, noise, vibration, bearing and oil pool temperatures, and seal leakage should be recorded. After passing the no-load test, perform air tightness inspection, and then perform load test on a sampling basis or one unit at a time.

The load test is closer to reality with proportional and graded loading: no load linkage ≥4 h, 25% load ≥16 h, 50% load ≥24 h, 75% load ≥48 h, and the tooth surface and temperature rise are observed step by step. The cost of doing everything is high. In practice, the choice is based on the importance of the model. However, "which levels will be done, how long will it be done, and who will record it" should be clearly stated in the agreement.

There are three recommended ways of witnessing: document witnessing (factory inspection report, material list, dynamic balancing record), video witnessing (full video recording of no-load operation and noise measurement), and on-site witnessing (buyer or third party arriving at the factory, notified 7 days before FAT). On-site witnessing is required for key units, and document witnessing is sufficient for general models. It is not necessary to upgrade all units.

5. Scope of supply: The interface is classified to the bolt level

A common dispute at the scene is not the reducer itself, but "who supplies this one?" Each item in the agreement should be ticked, and no blanks should be left.

project

common attribution

Remark

Reducer body and base

supplier

Includes nameplate, oil level mirror, breather cap, lifting lugs

Motor and connecting flange

According to the contract, the IEC flange number must be stated

Direct connection type must indicate the motor base and flange specifications.

Coupling, expansion sleeve, key

Usually the buyer must express

The hollow shaft expansion sleeve is usually supplied with the reducer.

Backstop/brake

Optional as needed

Inclined conveying must be checked. Missing supply will lead to back slipping.

Cooler, oil pump, oil pipe

Oil-cooled models are supplied with the supplier

For water cooling, please indicate the water quality and interface size.

Anchor bolts and pads

usually buyer

Specifications and grades are given in the agreement

First filling of lubricant

supplier

Indicate the brand number and filling amount

random files

supplier

Instructions, certificate, packing list, general drawing

6. Warranty and penalties: Write down the starting point and response time

There are two common loopholes in warranty terms: vague starting points and missing response times. The specification is "18 months from the date of acceptance of the goods, or 12 months from the date of operation, whichever comes first", and a separate line "If the installation is delayed for more than 6 months due to the buyer"s reasons, the warranty period shall be calculated from the 7th month after the arrival of the goods." This not only protects the buyer, but also prevents the supplier from bearing warehousing risks indefinitely.

It is recommended that the response terms be written in three paragraphs: a written reply within 24 hours after receiving the notification, a treatment plan within 48 hours, and arrival within 72 hours if on-site service is required (remote areas are subject to consultation). The penalty for delayed delivery is calculated at 0.5%/day, with a cumulative upper limit of 5%. If the upper limit is exceeded, the buyer has the right to terminate the contract - if the upper limit is not written, the penalty will lose its deterrent effect.

7. Three high-frequency misunderstandings

Only write the model number and not the operating conditions . The model number only describes the structure and base, but does not indicate how much impact the machine can withstand. The lifespan of the same model can differ by more than three times under uniform load and crusher operating conditions.

References to obsolete or inapplicable standards . Standards change versions frequently, so the agreement should write 'currently valid version', or directly state the version number and agree on how to deal with version changes, so as to avoid each party having a version of the standard for comparison during acceptance. Reducer product standards and noise and vibration measurement standards have been revised in recent years. You will not suffer any loss if you verify them before signing.

Missing interface division . Once the 'small items' such as couplings, anchor bolts, and cooling water connections are not clearly written down, work will be stopped on site. Table ticks are more reliable than textual descriptions.

Conclusion

A good reducer technical agreement reads like a checklist: each item has a numerical value, a standard number, a measurement method, and a responsible party. It does not increase the procurement cost, but just prices in advance any disputes that may occur later. After writing the first draft, it is recommended to do a self-examination - hand the agreement to a colleague who was not involved and ask him to answer 'where is this machine installed, how much torque it can carry, and how to judge whether it is qualified' using only words. Any areas that cannot be answered are the areas that need to be filled in.

Hangzhou Weigao Transmission can provide Selection accounting and agreement parameter filling support for hard tooth surface reducers , cycloidal pinwheel reducers, worm gear reducers and gear reduction motors, covering M1~M6 installation positions, service coefficient values ​​and thermal power verification, and can compare and replace installation dimensions and torque levels according to SEW, NORD and other brand models. As a reducer manufacturer , we can provide working condition review, drawing confirmation and factory inspection records according to the project; if you need free Selection accounting or agreement template, please contact us and send us the working condition parameters to get a verifiable Selection suggestion.

FEEDBACK

Apron Feeder Gearbox Selection: Chain Pull, Shock Load and Service Factor

How to determine the two-stage speed ratio of the cycloidal pinwheel reducer: how to read the combination table, how to check it, and how to find the frame number - Hangzhou Weigao Transmission

In addition to high temperature environments, what are the application precautions for R series gear reducers in other special environments?

How does the R series helical gear reducer perform in a strong vibration environment Selection

Pneumatic Conveying Gearbox Market 2027: Blower, Airlock and Screw Drive Demand